La
Brava
Bali
Imagine being the owner of a villa in Bali that you can enjoy and profit from at the same time. Obtain a 20% annual return and let go of all the management worries.
About
La Brava has created unique spaces that make it the ideal place for any visitor arriving in Bali. Our mission is to create personalized paradises, where every detail is meticulously designed to enhance the natural beauty of the island and provide accommodation full of comfort and harmony, blending luxury with the relaxed atmosphere of the Uluwatu area.
We are committed to offering exceptional experiences to our guests while simultaneously maximizing profitability for the property owners. We recognize the importance of providing a solid and sustainable return on investment through efficient management and a strategy focused on achieving the best results in Bali's real estate market.
At La Brava, we value excellence in design, attention to detail, and the satisfaction of both guests and property owners. Our goal is to become the preferred destination for accommodations in Uluwatu, leading in offering high-value and profitable properties. With passion and dedication, we are building a legacy of exceptional hospitality and unique spaces, ensuring mutual success over time.
Bingin Villas
In the picturesque area of Uluwatu, Bingin stands out as the epitome of premium real estate. La Brava Bingin Villas, nestled in this prime location offers being surrounded by nature, providing both privacy and tranquility while remaining close to all the local amenities. These villas feature high-quality finishes and materials with exclusive designs, ensuring minimal long-term maintenance and making them highly sought after on the island.
Interested in owning yours? Stay tuned for our upcoming projects as this promotion has been incredibly successful, and all available units are now sold out.
8 units - 2 bedroom villa - 290.000€ - SOLD OUT
9 units - 1 bedroom villa - 215.000€ - SOLD OUT
Bingin Villas
2 bedrooms
Bingin Villas
1 bedroom
Padang-Padang
Boutique Homes
We’re starting to build a new project of 10 boutique units close to Padang Padang Beach. Stay tuned. Sold out
Bingin Ocean
Residences
30 exquisite ocean-view residences, designed to redefine coastal living. Offering long-term extendable lease options, these exclusive homes combine elegance and serenity. Inquire now for early reservations.
Progress
Bingin
Villas
We started building the Bingin Villas development on November 1, 2023, and it has an estimated delivery date of December 15, 2024
Nothing is more exciting than being a part of the construction of your house and witnessing the progress. That's why in this space, we are sharing all the latest developments, allowing our investors to follow every new detail regularly. Stay connected for exclusive updates on our project's journey.
1. Start ploting
The initial phase involves meticulous planning and strategic plotting. Our team has engaged in a comprehensive process to outline and designate specific areas for construction. This step is crucial to ensure an organized and purposeful layout, aligning with the vision of the project. Starting with the plotting phase sets the foundation for a well-structured development, emphasizing precision and careful consideration in the utilization of the available land.
October 14, 2023
2. Cleaning and preparation of the land
Simultaneously, the clearing of the land is a fundamental step to prepare the canvas for construction. Thorough site clearing has been undertaken, removing any obstacles and ensuring a pristine starting point for the Bingin Villas. This process involves the removal of vegetation, debris, and any impediments that might hinder the construction process. Clearing the land not only creates a safe environment but also paves the way for subsequent phases, marking the beginning of the physical transformation of the site into a space that aligns with the project's architectural vision. The successful completion of the bow plank installation marks a pivotal moment, establishing the essential foundation necessary for future infrastructure development. An efficient temporary material storage area has been meticulously set up. This organized space ensures quick and convenient access to essential construction materials, optimizing workflow and minimizing potential delays. A robust infrastructure has been put in place to facilitate the construction of temporary housing and workplace sites. This strategic setup ensures that the project team has access to adequate facilities, supporting ongoing construction activities with efficiency. Additionally, a comprehensive infrastructure has been established to guarantee a constant supply of water and electricity. This commitment to reliable utility services creates an efficient working environment, fostering productivity and progress throughout the Bingin Villas construction process.
November 14, 2023
3. Earth work and foundations
In the EARTH WORK AND PONDATION phase, significant progress has been made: 1. Excavation for Continuous Foundation: Meticulous excavation has been carried out for continuous foundations, ensuring a solid and stable base for the structures. 2. Excavation for Foot Plate: Excavation necessary for the foot plate has been precisely completed, preparing the ground for the next construction phase. 3. Soil Fill for Floor Leveling: Strategic soil filling has been performed to achieve perfect floor leveling, ensuring uniformity throughout the property. 4. Sand Fill under Foundation: Careful and calculated sand filling under the foundations has been completed to provide additional stability and strength.
November 30, 2023
4. Concrete base
Crucial steps have been taken in accordance with the planned schedule for the project. Excavation necessary for the foundation has been initiated, carried out meticulously with the aim of establishing a solid and stable base for the future structures. Simultaneously, a strategic fill has been executed to achieve a perfect ground level throughout the property, ensuring uniformity on the surface. Additionally, the placement of the stone base has commenced, contributing additional stability and strength to the project.
January 31, 2024
5. Structures
In parallel, the application of concrete to the base structures has started, ensuring the necessary solidity for the ongoing development of the project. A significant milestone has been reached with the application of concrete to the columns of the ground floor of the villa/entrance, marking a noteworthy advancement in the overall construction. Furthermore, excavation necessary for the construction of pools has been initiated, integrating this key feature into the overall project. This progress reflects a rigorous commitment to the established schedule and establishes solid foundations for the subsequent phases of the project.
January 31, 2024
6. Retening walls
Considerable progress has been made according to the project's schedule. The construction of the retaining walls, executed with precision, marks a significant advancement in reinforcing the site's stability. These structures serve a crucial function in mitigating lateral pressures and preventing soil erosion. With the completion of the retaining walls, the groundwork has been laid for the next phases of the project. This update reflects the successful execution of planned tasks, moving the project forward effectively.
February 29, 2024
7. Wall Structures
Having completed the foundation structures and finished the retaining walls, we are now in the process of setting the wall structures for the second floor, as the first floor is already completed. This entails meticulous alignment and securing of the structural components to ensure seamless vertical expansion and structural integrity throughout the building. Our focus remains on precision execution and adherence to engineering standards as we advance towards the next phase of construction.
March 31, 2024
8. Roof Structures
Having completed the foundation structures and finished the retaining walls, we are now in the process of setting up roof structures in several of the houses, as the first-floor foundations are already completed. This entails meticulous alignment and securing of the structural components to ensure seamless vertical expansion and structural integrity throughout the building. We have procured all necessary materials for this process and are working diligently to complete the roof structures in the coming months. Our focus remains on precise execution and adherence to engineering standards as we advance towards the next phase of construction. It is worth noting that we are operating within specific deadlines and timelines for deliveries, which necessitates maintaining a steady and efficient pace in our work.
April 30, 2024
9. Electric work
Currently, in the construction phase we are in, we are at the initial stages of electrical and plumbing installations. These early steps are essential to laying the groundwork for a safe and efficient system that will ensure the functionality and comfort of the building once completed. At this initial stage of electrical installations, the technicians are beginning with the planning and routing for the wiring. The first conduits and junction boxes are being installed at strategic points throughout the building. This includes placing conduits in walls and ceilings to prepare for the electrical cables. Additionally, the optimal locations for electrical panels, switches, and outlets are being determined, ensuring everything aligns with the project’s plans and specifications.
May 31, 2024
10. Ceiling and exterior walls
Currently, we are in the phase where the roofs of the houses have already been constructed, and preparations for finishing work are underway. This involves getting ready to start the flooring installations and beginning to clad the exterior walls with stone. With the roofs now completed, the primary structure of the houses is solid and secure, providing a perfect foundation for the future development of the homes. The completion of the roofing ensures that the structural integrity of the buildings is maintained, allowing us to focus confidently on the next phases of construction. Simultaneously, work has begun on cladding the exterior walls with stone. This process involves careful preparation and installation to ensure a high-quality finish that enhances both the aesthetic appeal and the structural integrity of the buildings. Skilled masons are placing each stone with precision, following the design patterns and ensuring that the cladding is securely attached to the underlying structure.
May 31, 2024
11. Plumbing work and swimming pool
Simultaneously, the plumbing team is starting with the installation of the main pipes for the water supply and drainage system. This involves routing the paths for the pipes and the initial installation at key points in the building. High-quality materials are being used for the pipes to ensure their strength and durability. Basic connections for future water points, such as faucets and sanitary fixtures, are being established, although these elements have not yet been installed. Currently, we are in the advanced stages of constructing the swimming pools. With the excavation phase completed, we have moved on to the installation of retaining walls, structures, and the necessary mechanical and electrical plumbing systems, including the installation of pumps, we are making significant progress in the construction of the swimming pools. We will continue to advance with precision and dedication, ensuring the successful completion of this phase and laying the groundwork for the final stages of the project.
May 31, 2024
12. Interior distribution
The construction project is progressing according to the established schedule. We have completed the structures and installations, and now we are in the phase of distributing and implementing materials in the interiors. Currently, we are beginning with the installation of floors, interior wall coverings, and kitchen and bathroom fittings. Every detail is being carefully considered to ensure it meets the highest standards of design and functionality. The floors are being installed using high-quality materials to ensure durability and aesthetics. The interior wall coverings are also underway, with special attention to finishes and textures that will offer a sophisticated and cozy ambiance. In the kitchen, we are installing countertops, cabinets, and efficient storage systems, all designed to combine functionality and style. Additionally, we have started placing materials on the terrace and the swimming pool, ensuring that the outdoor spaces are equally impressive and functional.
August 31, 2024
13. Garden and external works
The construction project is advancing on schedule, and we have started the external works for the garden. Some of the plants have already been placed, and we are carefully designing the layout to create a beautiful outdoor space. We are also filling some of the pools to test and ensure everything is functioning perfectly. This phase marks a key milestone in preparing the outdoor areas, making sure the gardens and pools will enhance the overall experience once completed.
September 14, 2024
14. Finishing and painting
We’ve started painting the walls, carefully selecting colors and finishes to create the desired atmosphere in each space. Additionally, we are testing different textures for the walls and surfaces to ensure a refined and cohesive look throughout the property. These finishing touches are key in elevating the overall design and ensuring that every detail reflects the high standards we’ve set for the project.
September 30, 2024
15. Interior design and procurment
ETA: October 31, 2024
16. Test period
ETA: November 30, 2024
17. Villa ready for guests
ETA: December 14, 2024